Stuart Pepper Middle School
About the Project
Redlee was the General Contractor for the construction of this 102,400 square foot school, which includes both renovation and new structures.
Renovations included:
Demolition of front entry and Administrative suite
Replacement of existing water source HVAC system
Installation of all new LED light fixtures
New flooring, ceilings and paint through-out
Asphalt connection roads
Parent loop within the surrounding campus
Additional structures included:
Four science classrooms
Expanded & re-purposed mechanical room
Eight new tennis courts
New administrative wing
Gym with wood flooring & telescoping bleachers
Shared lobby space
2,400 square feet of mechanical mezzanine
For more information regarding this project, or to inquire about our services, please call Redlee Construction at (502) 412-3777 or email us at info@redleeconstruction.com.